Move Our Mission Groundbreaking event

October 31, 2019

 

Images from the “Move Our Mission” groundbreaking ceremony held at 1300 Martin Luther King Jr Blvd on October 31, 2019 for Rescue Mission of Mahoning Valley to begin construction of a 5.5 million dollar replacement shelter project.

 …

Read more

The footers were placed – May 2020

May 9, 2020

The footers were placed  – May 2020

Concrete was poured in July 2020

July 8, 2020

Walls went up in August 2020

August 4, 2020

September of 2020 saw lots of progress!

September 1, 2020

 

 

Read more

October 2020

October 9, 2020

November 2020 – time to start working inside!

November 9, 2020

January 2021 saw the men’s bunk rooms, chapel and dining hall really take shape.

January 9, 2021

 

 

Read more

Drywall, some kitchen appliances and the start of exterior siding were highlights in February 2021

February 9, 2021

So much progress inside in March 2021

March 9, 2021

April 2021 – the concrete was poured for the steps and ramp, floors were tiled and most of the siding was completed.

April 6, 2021

June 2021 – siding is complete, sidewalks are in and exterior lighting is placed.

July 9, 2021

The David L Sherrard Memorial Chapel is completed

October 4, 2021

Bedroom furnishings arrive for our Women and Families Deparment

October 18, 2021

Two 30 bed bunk rooms are prepared for male clients

November 2, 2021

Ribbon Cutting for the New Rescue Mission of the Mahoning Valley

November 12, 2021

Our first meal served in the new dining hall!

November 15, 2021